For Such A Time As This giving through January 28, 2003

Total Building Cost 11,500,000

Total Pledges 7,623,978

Recent Progress for the Building Project
  • FPC decides to expand December 2001
  • Giving Campaign initiated February 2002
  • Congregation pledges 5 times annual budget as a “First Fruits Offering”
  • Salinas Planning Commission votes 5-0 in favor of project September 2002
  • Evening of Prayer Planned for April 13, 2003
  • Project to begin April 2003
  • Demolition begins June, 17, 2003
  • Groundbreaking Ceremony June 25, 2003

     The Groundbreaking Ceremony was a hit!  Over 200 gathered for this significant event in the construction process of the new building.  There was excellent media coverage by the local television stations as well as the newspaper.  Red Bryan spoke on the reason FPC was building this worship center, Mayor Anna Caballero gave a very encouraging speech and Pastor Mike spoke about the significance of bringing Christ to Salinas .  The event ended with the actual ground breaking and prayer. 

  • Demolition ends July 11, 2003

  • Construction begins August 2003.
  • Bond Meetings October 6 & 7, 6:30-7:30
  • Blocking Complete November 19, 2003
  • Concrete Slab pouring November 19-26, 2003
  • Steel Framing Begins December 1, 2003
  • Steel "Topped Out" January 28, 2004
  • Concrete slab pouring on steel decking February 11-20, 2004